Notes of Community Meeting 18 June 2018

Notes from the 18thJune Community Meeting

Attended by members of CAG Liaison group, local residents and local business people.

Lori (Chair) gave an update on things as they stand:

  • Site is being cleared (as seen on site visit earlier in June). Wrings, the demo contractor, have done a lot of work but it’s been harder and slower they anticipated (they had expected to demolish in March). Asbestos and other contaminants have been found and must be properly dealt with.
  • Problems with ecology licences especially bats – licence granted did not allow sufficient time to carry out works required.
  • 4 Ashley Road has gone. Materials have not been repurposed. Some discussion about how bad the condition of the building was and what could have been saved.
  • New target is to complete demolition by September.
  • PG still holding to target completion date (to the original planning permission) of summer 2020.
  • Quite a lot of difficulty in communications with PG – not responsive or actively engaging in discussions.

Cultural Plan

Willis Newson have been appointed by PG Group to progress this work. Challenge is that there are no, or few, precedents from elsewhere as to what a Cultural Plan for a development like this should be. The planning permission requires that CAG and the community be involved.

Planning Condition 15 (7 July 2016). Prior to the commencement of any construction works for the development a Cultural Programme Delivery Plan shall be submitted to and approved in writing by the Local Planning Authority. This shall set out the details of the Cultural Programme Steering Group, co-ordinated by an appointed programme manager. This Delivery Plan shall set out clear principles for the delivery of cultural projects to be delivered within the site. Reason: In the interests of the proper management of the site.

Willis Newson are holding 1:1 meetings and focus groups over the summer. These will inform the contents of a widely distributed questionnaire in September. Comment that they seem to be harvesting information but not presenting any of their own thoughts or processing / sharing the information received.

Concern that Willis Newson’s approach has adopted an emphasis on public art and that they’re talking mostly to arts organisations and not to a broad cross-section of organisations that inform the social, economic and environmental culture of the area around the site. Residents also seem to have been left out of the consultation.

Message to WN is that the local community want a meeting with them. Need date asap so that it can be publicised.

Question of who defines the area? Recently there has been gentrification by people who have moved in and have different perceptions of the area. We’re trying to define our heritage – that’s why No.4 was important but now it’s gone.

The development needs to be a place where everyone feels as comfortable as possible – somewhere that is welcoming.

CAG’s view of the Cultural Plan is that it should include and set out uses of the ground floor and how they will complement the area.

Ownership of the ground floor of the finished development is more important than sculpture, in part because who owns will define what happens in the space.

Community Ownership

PRSC asking why there’s nothing coming back to the community? Conversation moved towards whether there should be an element of community ownership. There should be a partnership element to get the cultural plan going.

Graffiti is a red herring. There needs to be an element of community ownership under a land trust. Response from WN is that they are open to this. PG have been a brick wall. This should be a business pitch to PG.

The space needs to be controlled by local groups forever so that it can be something different in years to come if needed.

2 or 3 units need to be connected to the functions in the market space.

You want to control who the units are rented to – it shouldn’t be random. The level of control and who’s involved (should include residents and unit occupiers) needs to be carefully worked out. Keeping rents low is also key. The Cultural plan and management plan overlap. If we can’t stop WN going down the community arts route with the cultural plan then the management structure will finish up outside of our remit and beyond our influence.

Planning Condition 29 (7 July 2016): Prior to the occupation of each of the commercial unit(s) facing Stokes Croft and Ashley Road by any A1, A3, A4, A5, D1 and D2 use (or combination thereof) hereby permitted a management strategy should be submitted to and approved in writing by the Local Planning Authority. The scheme should to include the following unless otherwise agreed in writing by the Local Planning Authority:

(a) Confirmation of the tenant mix

(b) The way in which the floorspace (layout) will be used

(c) How the tenants will manage their servicing requirements (including confirmation of refuse and recycling storage within the units and how this will be accessed, the number and type of vehicles arriving at the site each day to deliver and collect goods and what refuse and recycling items are to be collected from where and when

(d) Location and operation of staff cycle storage

The floorspace shall be occupied in accordance with the approved details and strategies in perpetuity. Any subsequent occupiers of the commercial unit(s) (in perpetuity) shall submit a new management strategy to the Local Planning Authority for approval prior to occupation

Reason: To ensure responsibility for the management of these facilities and to safeguard the appearance of the development, highway safety and the amenities of future and existing residents and businesses.

Recognition by everyone present that you can’t separate management plan and culture plan – they are integrated. Each is the other. Unanimous agreement on this statement.

Comment that PG are taking an old-fashioned approach. The community’s approach should be we want the whole of the ground floor. It’s in PG’s best interests. If it worked well it would really uplift the whole development. Selling them a business case is the way to go about it. Showing them how to deliver a different business model. We can hand something to PG to do something different.

The Identity of the Development

Montpelier Con Group wrote to WN and said they wanted to see the work of Godwin celebrated. This raises an issue of what the development should be called. Discussion about the name and identity of the scheme and the area.

Not Godwin Yard as shown in the planning application although the term ‘yard’ is Jamaican for garden so has local resonance.

Comment that it’s not Godwin in the way that Montpelier CG think of him, it’s the idea of Godwin – a free thinker and polymath who opposed mean spiritedness of developers and businesses.

Are we agreed that Godwin is important? Answer: yes

Housing

A lot happening in the background, although not as far forward as wanted. Scheme with planning permission has 10 affordable units.

HCA gave BCC funding of just under £1m with assumption it would be used for CPO. When PG group came along and took ownership the Council decided some of it could be offered to PG to up the number of affordable units. Has taken a long time to get that discussion underway.

There are people locally who want to downsize. Carriageworks could offer them great options and ensure that local residents move in. Need somewhere for local people to put their name down as interested purchasers.

Materials

Planning Condition13. Notwithstanding any materials noted on any approved plans, sample panels of all the external materials and finishes to all buildings, associated plant areas, walls, hard landscape features including paved surfaces, demonstrating coursing, jointing and pointing to the masonry, are to be erected on site and approved in writing by the Local Planning Authority before the relevant parts of the work are commenced, unless otherwise agreed in writing by the Local Planning Authority. The development shall be completed in accordance with the approved details, unless otherwise agreed in writing by the Local Planning Authority.

Reason: To ensure that the external appearance of the building is satisfactory and that the character, appearance and setting of surrounding Conservation Areas and Listed Buildings would not be harmed.

Don’t know what the timescale on this will be (but has to before development starts).

They should be thinking about using local suppliers, crafts etc.

Materials could be included in WN consultation in Sept.

 

Advertisements

Notes of Community Meeting on 10 January 2018

The meeting with CAG and local residents was attended by representatives of PG Group, Bray and Slaughter and Wring Group.

Timetable

There has been a 4-6 week delay from the previously anticipated January start. Exact timetable is dependent upon many ongoing investigations. Current timetable is roughly:

  • February: Erect site scaffolding to make it secure, protect adjoining properties and prepare for the next steps.  3 – 4 weeks total.
  • March: Demolition of Westmoreland House begins. Demolition is likely to take 16 – 20 weeks. Timescale hard to predict but will be informed by ongoing surveys and investigations.

Surveys

  • During demolition of Westmorland House there will be ongoing investigations into the condition  of the Carriageworks building.
  • Cellars and curtilage extent is being investigated for both buildings
  • Party wall matters are being discussed and drawn up with neighbours
  • Asbestos and other surveys such as contaminated soils will be completed prior to demolition and mitigated.

Site Security, Fencing and Pedestrians

  • Both frontages of the site will be fenced off to 2.5m from the building line but still within the curtilage
  • Pavements will be closed while the scaffolding is being erected
  • When the Carriageworks and Westmorland House façades are stabilised a pedestrian ‘protected tunnel’ will be installed on Stokes Croft under the support system
  • The Ashley Road pavement outside the site will be closed. Pedestrians will use a temporary crossing to the Picton St side of the road then back across at the Cheltenham Road junction
  • Site hoardings are expected to be managed and decorated by local artist community.

Demolition

Contractor: Wring Group Ltd

  • Working Hours are expected to 8am – 5pm winter and 8am – 6pm summer (this applies to both the demolition and construction phases)
  • Plan for services disconnections and reconnections are being drawn up
  • Demolition process will include a ‘Man in the Cage’ approach where Westmorland House is semi-tented and a water shrouded ‘nibbler & cutting’ process used for dismantling the structure
  • The water shroud will minimise the dust and noise footprint to ‘about’ ambient for the area
  • There will be ‘debris shelters’ to protect ‘Tuckets Building’ and other adjacent properties
  • With the exception of any steelwork the majority of demolition spoil will be retained on site for reuse as processed hard core and other uses
  • Due to the recycling of materials only one large truck load a day is expected to leave the site
  • Site clearance of earth to dig down to building levels is subject to separate removal.

Archaeology and Recording

  • If cellars are found they will be left exposed for Party Wall discussion and redesign of the Carriageworks lower floors
  • Archaelogy Surveys will run in parallel with the demolition process. Work will stop when necessary for identification, recording and possible removal
  • Grade 2* listing also applies to other Carriageworks features such as steel columns and cellars.
  • The demolition and building process will be recorded:
    • Salvation Army have granted provision to have a fixed camera mounted on their retaining wall to record progress
    • A Dove Street flats resident is to be asked to have a fixed camera on their balcony rail to record progress.

Traffic Management

  • The greatest period of disruption will be while the scaffolding is going up. During this time, the pavements outside both buildings on Stokes Croft will be closed, and traffic might be controlled by temporary traffic lights
  • Traffic Management during demolition phase is not likely to be a major issue
  • The published Draft Traffic Scheme for Stoke Croft will be subject to revision once  cellar and curtilage investigations are complete
  • Once the scaffolding is erected two-way traffic will be maintained on Stokes Croft during construction and demolition
  • There is an expected loss of two parking bays on the Ashley Road frontage
  • We will aim to keep you updated about all this, as it’s a changing picture.

Architecture

  • Finishes and brickworks selection subject to approval by BCC
  • Peter Westbury (for BCC) will sign off finishes following public consultation
  • A photographic record is complete and on show in The Elemental Café (bakery on corner of Nine Tree Hill and Cheltenham Rd)

Construction

Contractor: Bray and Slaughter

  • Considering a separate specialist historic building sub-contractor for the Carriageworks
  • One large 45m reach Luffing Crane will be located near the centre of the Market Square. It will not over-swing adjacent properties or weathercock with the wind when not in use. Consequently no wayleave to overfly adjoining properites will be required
  • Other Cranes will be a mix of mobile units for the houses and lower elements
  • No information is yet available on concrete mixing and whether this will be on- or off-site
  • Local job creation including new apprenticeships will be managed by Bray & Slaughter and Wrings

Affordable Housing

  • As yet there is no change to the number of units marked as ‘Affordable’ although PG Group have now arranged to meet Council officers to discuss opportunities to use available funds to create additional affordable units
  • It is expected that the ‘Affordable Units’ will be for shared ownership and will be located in a single block
  • Generally all sales will be on an ‘open market’ basis

Cultural Plan

  • By the end of January a Public Art and Cultural Plan must be lodged with Bristol City Council to comply with planning conditions
  • Willis Newsom has been appointed to manage the Cultural Plan
  • When completed (Apr-May 2018) the Community Framework will be presented to the public for consultation
  • The Cultural Plan may inform the Public Art issues
  • The wider area and not just current use of the street of Stokes Croft will inform the Cultural Plan and will be made available for the site sales material
  • A degree of control over the use and business types for the ground floor commercial units and market area will be exercised to reflect the wider cultural influences not just the current use of Stokes Croft

Next Meeting

To be confirmed but expected to be quarterly.

Planned Road and Pavement Closures + Other Site Management Issues

On 1 December the City Council approved PG’s proposals for road and pavement closures around the site during demolition and construction.

The proposals form part of the ‘Construction Environment Management Plan‘ (pdf) and were submitted in September. This can also be found on the Council’s planning website.

The Plan addresses the following:

Communications

PG’s communications consultant, Jenny Gee, will be “working closely…to establish a working relationship that builds trust” with CAG, neighbours and businesses. Communications will include “sharing both the overall build plan and daily on-site activity” with a commitment to responding to questions by the end of the next working day.  Local residents will receive quarterly update letters.  Daily updates will be available from the site communications website  – https://consultingyou.co.uk/carriageworks.

Complaint Management

Any complaints should be submitted via PG’s communications website or in writing to Jenny Gee Communications, 2 Fernbank Road, Redland, Bristol, BS6 6PZ.  Responses will be provided by the end of the next working day.

Hours of Operation

Works will take place Monday to Friday 8am to 6pm and Saturday 8am to 1pm.

If any work is required on Sundays or Bank Holidays advance consent will be sought from Bristol Planners.

Deliveries

There will be no major vehicle movements into or out of the site during the school run. Actual times still to be agreed with the City Council.

There will be a full-time ‘gateman’ at the Ashley Road entrance.  Vehicles will normally turn around on the site but, if the need arises, the gateman will control traffic on Ashley Road to enable vehicles to reverse in.

Control of Dust

(The dirty sort not Rusakov Particles, which are altogether harder to contain).

Dust will be created during demolition. Dust suppression will include damping down with sprayed water during demolition, crushing and storage; sheeting and screening; enclosure of skips; watering of haul routes; sheeting of vehicles removing demolition materials and siting of the crusher as far as possible from neighbouring properties.  Burning of materials on site will be strictly prohibited.

Lighting

To avoid light spillage onto residential properties, temporary lighting will only be used when absolutely necessary; directional lighting will be used instead of floor lighting; low level and sensor controlled lighting will be used only during hours of operation; physical screening will be provided.

Parking

Site workers will not be able to park on site and will therefore park in the surrounding areas.  (No mention is made that these areas are RPZs)

Temporary Traffic Measures

The following drawings set out the proposed measures.  The dates are CAG estimates. PG will confirm final arranagements once they are approved by Bristol City Council Highways.

Phase 1 (¿January 2018?)

Erecting (and later dismantling) the temporary façade support system to the frontage of the  Carriageworks.

Phase 2 (¿January – March 2018?)

Demolition of Westmorland House

Phase 3 (¿April 2018 – sometime in 2019?)

Construction works until the new internal structure of the Carriageworks has been completed. The façade support system is then removed.

Phase 4 (¿2019-2020?)

Construction works following removal of the temporary façade support structure to the Carriageworks.

Phase 5 (¿2019?)

Construction of a new manhole over the existing Wessex Water combined sewer in Ashley Road, very close to the traffic light controlled junction with Stokes Croft. This will, in all likelihood, be a deep excavation which will necessitate a temporary road closure (see SK5). This has been discussed in principle with BCHDH and would be timed to take place during a school holiday period.

Other Road Closures (¿2018-2019?)

It may also be necessary to close Ashley Road for 1 day for the erection (and 1 day later for dismantling) of a tower crane.