PG Group Proposals and Timetable

The Carriageworks Liaison Group have met with the PG Group to discuss their proposals.  We understand that there will be no changes to the scheme granted planning permission in July 2016 (as approved by Planning Committee October 2015) that would require a new planning application (although minor alterations will be sought).

Ground Floor Plans, Aug 2015

Timescale

Summer 2017 – appoint design team, site investigations and surveys, building regs, planning pre-commencement conditions etc

October 2017 – demolition begins

January 2018 – construction begins

Summer 2020 – completion of development

 

Update (September 2017)

November 2017 – demolition begins

March 2018 – construction begins

Dec 2020 – completion

 

[First published: 12 June 2017]
[Updated: Sept 2017]